Hart & Hickman conducted soil, sediment, groundwater and surface water assessment, prepared closure plans & designs, and closed the unpermitted Lily Glen disposal site for Springs Industries. Approximately 50,000 tons of mill debris were graded and capped. H&H assessed soil and groundwater conditions, delineated horizontal and vertical extent of waste and debris, obtained the necessary erosion control permits, and constructed an interim cap.